page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
page 186
page 187
page 188
page 189
page 190
page 191
page 192
page 193
page 194
page 195
page 196
page 197
page 198
page 199
page 200
page 201
page 202
page 203
page 204
page 205
page 206
page 207
page 208
page 209
page 210
page 211
page 212

Hawaiian Dredging Construction Co.: Beach Walk Waste Water Pump Station August 09 www. bus- ex. com 145 much a long- term project. The team consisted of the City and County of Honolulu, owner; Hawaiian Dredging Construction Company, general contractor; Healy Tibbits, marine subcontractor; Frank Coluccio Construction Company, micro-tunneling subcontractor; Wasa Electric, electrical subcontractor; Associated Steel Workers, ironworkers subcontractor; M& E Pacific, construction manager for the City and County of Honolulu; R. M. Towill, design consultant; Yogi Kwong Engineers, geotechnical design consultant; Kai Hawaii, civil design consultant; and Ronald Ho & Associates, electrical design consultant. Action had to be taken quickly, however, because the Environmental Protection Agency had given the authorities a very tight deadline of just over three months to complete the bypass phase, by July 31, 2006. " When the team first met we knew what had to be done, but we didn't know how we were going to do it," Chang explains. " From that day we started on the design work, and it was very much design on the fly." Alongside HDCC on the team were Healy Tibbitts and Coluccio Construction Company. Roughly 5,000 feet of 48- inch HDP pipe was to be anchored along the bottom of the Ala Wai by Healy Tibbitts. Meanwhile HDCC, which was project-managing the operation, was to construct all the above- ground work: laying pipes along both sides of the canal and installing manifolds and pumps to collect the sewage from each of the manholes and pump it into the main 48- inch pipe. The demanding time schedule introduced huge constraints and challenges into the project, one of the biggest problems being sourcing materials for delivery within such a timeframe. " Procuring the HDP pipe in that quantity and size, for example, was really challenging. Nobody buys that type of pipe anymore, so we had to have it made," Chang says. " Because this order was of such a critical nature, the vendors we contacted were prepared to stop all other operations and accommodate our order- if they received it right away." Acting quickly, the Honolulu authorities authorized HDCC to procure the pipe just days after the first meeting. " This was before we even had a contract with them," Chang says. " But it was a good decision. We committed roughly $ 3 million to the order, and the pipe began to arrive just a month and a half later." By working 24 hours a day on some occasions, the bypass was opened on time. However, sourcing pumps for the operation had also been difficult, and for a while the bypass had to operate with just three of the seven pumps the authorities has asked for, the remaining four being installed when they were received. The second phase of the project was to construct a permanent underground sewer line from the original pumping station at Beach Walk, Waikiki, under Kaiolu Street and the Ala Wai Canal to a new station where it would be tied into the 48- inch HDP pipe running along the canal bottom. Beach Walk pumping station could then be brought back online, and all the temporary pipework and pumps that had been part of the original bypass and had been pumping the sewage directly from the manholes could be removed. Using micro- tunnelling technology- a process that Coluccio specialized in- the pipe was laid by tunnelling underground rather than trenching. " We built the receiving shaft while Healy Tibbitts and Coluccio built the jacking shaft. They then had to construct two tunnels between the shafts, and they had to be exactly on target." In total, HDCC laid close on 12,000 feet of pipe at a depth of about 36 feet below ground. " We also met the city's deadline of June 30, 2008, for getting the pumping station back online," Chang says. " In total, this second phase took from July 2006 to January this year." One of the factors that made this job both challenging and rewarding for HDCC was the collaborative nature of the work, and the fact that the design work progressed with the project. Meetings were held between all the members of the team each week, thrashing out operational and design issues and keeping all the stakeholders informed of progress. " As a company," Chang says, " we have a philosophy of delivering service to the owner of the project. And we operate by keeping everybody notified. This has been a great project for us. It began as emergency work, but it has enabled us to build some really good relationships with people from the City, and that is simply invaluable."

146 www. bus- ex. com August 09 With Hawaiian Electric Company's new peaking power facility on Oahu built by Hawaiian Dredging Construction, blackouts are a thing of the past, David Hendrick reports Keeping thelightson W hen President Barack Obama and his family visited his childhood homestead in Hawaii last Christmas, the island unfortunately experienced an embarrassing power blackout